Temporary Traffic Lights
24 viewsRoadworks on Arundel Crescent, Plymouth
National Grid Electricity Distribution (south West) are responsible for these works from 27 Aug 2026 to 10 Sept 2026. Ends in 4d 15h.
Current status
Live
Ends in 4d 15h
Start
27 Aug 2026, 09:42
End
10 Sept 2026, 15:30
Estimated progress67%
Updated 27 Aug 2026, 10:16 (UK)
Ground report
Is it there?
Map
Details
- Works / promoter
- Utility Asset WorksNational Grid Electricity Distribution (south West)
- Work category
- Standard
- Reference
- LN0282578972A-01
- Official status
- Work Started
- Last updated
- 27 Aug 2026, 10:16
Timeline
- Work Started
- Permit Granted
- Permit Altered
- Permit Submitted
Roadworks data on this page is sourced from the Department for Transport.