Road Closed
179 viewsRoadworks on Eagle Street, Coventry
Cadent Gas Limited are responsible for these works from 24 Aug 2026 to 8 Sept 2026. Ends in 2d 23h.
Current status
Live
Ends in 2d 23h
Start
24 Aug 2026, 12:32
End
8 Sept 2026, 00:00
Estimated progress79%
Updated 24 Aug 2026, 12:38 (UK)
Ground report
Is it there?
Map
Details
- Works / promoter
- Utility Asset WorksCadent Gas Limited
- Work category
- Major
- Reference
- AZ5041001510327-02
- Official status
- Work Started
- Last updated
- 24 Aug 2026, 12:38
Timeline
- Work Started
- Permit Altered
- Permit Granted
- Permit Submitted
Roadworks data on this page is sourced from the Department for Transport.