Give-and-take Priority

Roadworks on Littlebrook Road, Ashford

Uk Power Networks South Eastern are responsible for these works from 16 Jul 2026 to 23 Sept 2026. Ends in 62d 19h.

Current status

Live

Ends in 62d 19h

Start

16 Jul 2026, 18:00

End

23 Sept 2026, 18:00

Estimated progress9%

Updated 17 Jul 2026, 08:10 (UK)

Ground report

Is it there?

Map

Details

Works / promoter
New Service ConnectionUk Power Networks South Eastern
Work category
Major
Reference
KZ50035329399-02
Official status
Work Started
Last updated
17 Jul 2026, 08:10

Timeline

  1. Work Started
  2. Permit Granted
  3. Permit Submitted

Roadworks data on this page is sourced from the Department for Transport.