Works With No Carriageway Incursion

Roadworks on Portland Walk, Barrow-In-Furness

Sp Electricity North West are responsible for these works from 16 Jul 2026 to 22 Jul 2026. Awaiting end confirmation.

Current status

Live

Awaiting end confirmation

Start

16 Jul 2026, 09:30

End

22 Jul 2026, 00:00

Estimated progress100%

Updated 16 Jul 2026, 11:20 (UK)

Ground report

Is it there?

Map

Details

Works / promoter
Optional Permit (no Fee) E.g. For Traffic Management EtcSp Electricity North West
Work category
Standard
Reference
JG808DLO_DOM5500370979-03
Official status
Work Started
Last updated
16 Jul 2026, 11:20

Timeline

  1. Work Started
  2. Permit Altered
  3. Permit Granted
  4. Permit Submitted