Temporary Traffic Lights
24 viewsRoadworks on Saint Aidans Terrace, Houghton-Le-Spring
Cityfibre Metro Networks Ltd are responsible for these works from 4 Sept 2026 to 5 Sept 2026. Awaiting end confirmation.
Current status
Live
Awaiting end confirmation
Start
4 Sept 2026, 11:45
End
5 Sept 2026, 17:00
Estimated progress100%
Updated 4 Sept 2026, 12:05 (UK)
Ground report
Is it there?
Map
Details
- Works / promoter
- Utility Asset WorksCityfibre Metro Networks Ltd
- Work category
- Minor
- Reference
- KG061PSN-PH4ST1-WP2OVER1-02
- Official status
- Work Started
- Last updated
- 4 Sept 2026, 12:05
Timeline
- Work Started
- Permit Granted
- Permit Submitted
Roadworks data on this page is sourced from the Department for Transport.