Road Closed
151 views

Roadworks on The Landway, St Pauls Cray

Southern Gas Networks Plc are responsible for these works from 24 Aug 2026 to 25 Sept 2026. Ends in 20d 3h.

Current status

Live

Ends in 20d 3h

Start

24 Aug 2026, 08:00

End

25 Sept 2026, 00:00

Estimated progress36%

Updated 24 Aug 2026, 08:25 (UK)

Ground report

Is it there?

Map

Details

Works / promoter
Utility Repair And Maintenance WorksSouthern Gas Networks Plc
Work category
Major
Reference
XW016W122907130-01315-04
Official status
Work Started
Last updated
24 Aug 2026, 08:25

Timeline

  1. Work Started
  2. Permit Altered
  3. Permit Altered
  4. Permit Granted
  5. Permit Submitted