Some Carriageway Incursion

Roadworks on Westfield, Plymouth

Connected Kerb are responsible for these works from 22 Jul 2026 to 28 Jul 2026. Ends in 5d 1h.

Current status

Live

Ends in 5d 1h

Start

22 Jul 2026, 09:00

End

28 Jul 2026, 00:00

Estimated progress10%

Updated 22 Jul 2026, 09:18 (UK)

Ground report

Is it there?

Map

Details

Works / promoter
Utility Repair And Maintenance WorksConnected Kerb
Work category
Standard
Reference
5A003P-015119-WESTFIELD-02
Official status
Work Started
Last updated
22 Jul 2026, 09:18

Timeline

  1. Work Started
  2. Permit Granted
  3. Permit Submitted

Roadworks data on this page is sourced from the Department for Transport.

Street Manager (DfT)